PMS 5.0 Report Updates¶
PMS has many generated reports via Excel exports and WFS exports.
In version 5.0 the PMS database underwent major changes, with all works
tables and data being migrated to
a new projects
data schema. This required many changes to database views and reports which are documented below.
Form B¶
‘Works Code’ column changed to ‘Project Code’
‘Works Name’ column changed to ‘Project Name’
‘Works Type Code’ column changed to ‘Majority Intervention Code’
‘Proposed Surface Type’ column changed to ‘Majority Surface Course Before’
‘Completed Surface Type’ column changed to ‘Majority Surface Course After’
‘Estimated DTTAS Grant Category Cost’ column changed to ‘Estimated DoT Grant Category Cost’
‘DTTAS Grant Category Cost’ column changed to ‘DoT Grant Category Cost’
‘StartX_b’ and ‘StartX_a’ columns changed to ‘Start Eastings (ITM)’
‘StartY_b’ and ‘StartY_a’ columns changed to ‘Start Northings (ITM)’
‘Works Id’ column changed to ‘Project Id’
‘JobCode’ column removed - ‘Project Code’ will be used for its value
Surface Material Report¶
This is available on the report dashboard under Report Links > Other Reports > Surface Material Report.
Export name: SurfaceMaterialSummary.xlsm
Data tab:
‘Surface Material’ column displays Material Name instead of old WearingCourse Abbreviation
‘Full Name’ column hidden (it was WearingCourse Name now Material Name above used only)
SurfaceMaterialbyClass tab:
some minor layout changes due to higher amount of possible Materials now
Data tab and Majority tab:
added new colour formatting for ‘Surface Material’ due to higher amount of possible Materials now - new colours picked randomly
LA-wide Mechanical Data Export¶
This is available on the report dashboard under Report Links > Other Reports > LA-wide Mechanical Data Export.
Export name: MechanicalDataSummary.xlsx
StripMaps tab:
‘Surface Material’ column displays Material Name instead of old WearingCourse Abbreviation
added new colour formatting for ‘Surface Material’ due to higher amount of possible Materials now - new colours picked randomly
Completed Projects and Current PSCI Rating¶
This is available on the report dashboard under Report Links > PSCI (Pavement Surface Condition Index) Reports > Completed Projects and Current PSCI rating.
Export name: ProjectsAndRatings.xlsx
Renamed => “Completed Works and Current PSCI rating” from “Completed Projects and Current PSCI rating”.
output filename changed from ‘WorksAndRatings.xlsx’ to ‘ProjectsAndRatings.xlsx’
report header changed from ‘Completed Works and Current PSCI rating’ to ‘Completed Projects and Current PSCI rating’
‘Works Type’ column changed to ‘Intervention Type’ and displays Intervention Type Name instead of old Works Type Code
back-end export service changed from ‘/export/worksAndRatings’ to ‘/export/projectsAndRatings’
Project Level PSCI Surveys¶
This is available on the report dashboard under Report Links > PSCI (Pavement Surface Condition Index) Reports > Project Level PSCI Surveys.
Export name: ProjectsSurveysCoverage.xlsx
Renamed => “Completed Projects and Current PSCI rating” from “Completed Works and Current PSCI rating”
output filename changed from ‘WorksSurveysCoverage.xlsx’ to ‘ProjectsSurveysCoverage.xlsx’
‘Percentage (of works) Surveyed Once’ column changed to ‘Percentage (of projects) Surveyed Once’
‘Percentage (of works) Surveyed At Least Twice’ column changed to ‘Percentage (of projects) Surveyed At Least Twice’
back-end export service changed from ‘/export/worksSurveysCoverage’ to ‘/export/projectsSurveysCoverage’
back-end dashboard service changed from ‘/dashboard/worksSurveysCoverage’ to ‘/dashboard/projectsSurveysCoverage’
All Works Report¶
This is available on the report dashboard under Report Links > Projects Reports > All Projects Report.
Export name: AllProjects.xlsx
Renamed => “All Projects Report” from “All Works Report”
output filename changed from ‘AllWorks.xlsx’ to ‘AllProjects.xlsx’
report header changed from ‘All Works’ to ‘All Projects’
‘Works Name’ column changed to ‘Project Name’
‘Works Phase’ column changed to ‘Project Phase’
‘Works Type’ column changed to ‘Intervention Type’ and displays Intervention Type Name instead of old Works Type Code
‘Works Id’ column changed to ‘Project Id’
back-end export service changed from ‘/export/works/all’ to ‘/export/project/all’
‘Surface_b’ column changed to ‘Majority Surface Course Before’
‘PSCI_b’ column changed to ‘PSCI Before’
‘IRI_b’ column changed to ‘IRI Before’
‘Length_b’ column changed to ‘Planned Length’
‘Area_b’ column changed to ‘Planned Area’
‘Width_b’ column changed to ‘Planned Width’
‘Cost_b’ column changed to ‘Cost’
‘% of Total Cost_b’ column changed to ‘% of Total Estimated Project Cost’
‘UnitCost_b’ column changed to ‘Estimated Unit Cost’
‘Surface_a’ column changed to ‘Majority Surface Course After’
‘PSCI_a’ column changed to ‘PSCI After’
‘IRI_a’ column changed to ‘IRI After’
‘Length_a’ column changed to ‘Actual Length’
‘Area_a’ column changed to ‘Actual Area’
‘Width_a’ column changed to ‘Actual Width’
‘Cost_a’ column changed to ‘Cost’
‘% of Total Cost_a’ column changed to ‘% of Total Actual Project Cost’
‘UnitCost_a’ column changed to ‘Actual Unit Cost’
‘Existing Surface Material’ column removed
some columns not populated yet; to be finalised after Form B report is completed
Pavement Works Project¶
This is available on the report dashboard under Report Links > Dynamic Reports > Pavement Works Project.
Export name: PavementWorksProject.xlsx
The view used by this report is also used for the WFS export service “Pavement Project Export”.
‘Works Code’ column changed to ‘Project Code’
‘Works Name’ column changed to ‘Project Name’
‘Works Type Code’ column changed to ‘Majority Intervention Code’
‘Existing Surface Type’ column removed
‘Proposed Surface Type’ column changed to ‘Majority Surface Course Before’
‘Completed Surface Type’ column changed to ‘Majority Surface Course After’
‘StartX_b’ and ‘StartX_a’ columns changed to ‘Start Eastings (ITM)’
‘StartY_b’ and ‘StartY_a’ columns changed to ‘Start Northings (ITM)’
‘EndX_b’ and ‘EndX_a’ columns changed to ‘End Eastings (ITM)’
‘EndY_b’ and ‘EndY_a’ columns changed to ‘End Northings (ITM)’
‘Works Id’ column changed to ‘Project Id’